The short answer
- Lead time is the time between the start of a process and its end, for example from placing an order to receiving the goods.
- The main kinds are supplier lead time, total (procurement) lead time, manufacturing lead time and customer order lead time. Each has its own start and stop.
- A useful split is pre-processing (need seen to order sent), processing (supplier makes and ships) and post-processing (received, inspected, put away).
- The quoted lead time is a promise; the actual lead time is measured from dates in the system. Planning works best on the actual one, with its spread, not only its average.
- Lead time and its variation drive the reorder point and the size of safety stock.
What is lead time?
In supply chains, lead time is the elapsed time between a trigger and a result. The trigger might be a customer order, a purchase order, or the moment a planner sees stock is low. The result might be goods at the customer, goods at the dock, or goods ready to pick.
Because the start and end can be drawn in different places, the same part can honestly have several lead times. Suppose a component takes 2 days to make, 3 to ship and 1 to put away. A buyer quoting the supplier may say 2 days, a planner including transport says 5, and the line that uses it waits 6. Nobody is wrong; they are timing different stretches.
The types of lead time
| Lead time | Clock starts | Clock stops |
|---|---|---|
| Pre-processing (internal) | need is identified | purchase or work order released |
| Supplier lead time | PO received by the supplier | goods shipped, or delivered, as agreed |
| Transit time | goods leave the supplier | goods arrive at the buyer's dock |
| Post-processing | goods at the dock | received, inspected, put away and available |
| Total (procurement) lead time | need is identified | goods available to use |
| Manufacturing lead time | work order released | finished goods in stock or shipped |
| Customer order lead time | customer order entered | goods delivered to the customer |
The supplier lead time stops at shipment or at delivery depending on the contract and the Incoterm; it is worth writing down which.
For products with many levels of parts, planners also talk about cumulative lead time: the longest chain of buying and making steps needed to produce the item from scratch. It sets how far ahead a plan must look in MRP.
How to measure lead time
Measuring lead time means choosing two timestamps that already exist in the systems and subtracting them, order by order. For supplier lead time that is often PO date to goods receipt date; for customer lead time, order entry date to delivery date. Comparing the actual with the requested date (what the customer wanted) and the confirmed date (what was promised) shows where the gap comes from.
- Use many orders, not one. Look at the average and the spread: the standard deviation, or a high percentile such as the 90th.
- Weight by volume where orders differ greatly in size, so one tiny rush order does not distort the picture.
- Keep the same start and stop across suppliers and periods, or comparisons mean nothing.
- Compare with the master data value that planning actually uses, and note how far apart they are.
Lead time vs cycle time vs transit time
These are often swapped. Lead time is what the customer of a process waits, from request to result, including any queue before work starts. Cycle time usually means the time a process actively spends on one unit or one order once work begins. Transit time is only the travel part. A supplier can shorten its cycle time and still deliver late if orders wait in its queue.
Common lead time mistakes
Questions to ask before you act
- Which two dates start and stop the lead time used in planning?
- Does it run to the moment goods can be used, or only to the dock?
- How far is the master data value from the measured average, and from the 90th percentile?
- Which stretch varies most: internal, supplier, transit or receiving?
Frequently asked questions
What is lead time in supply chain?
The time between a trigger, such as placing an order, and a result, such as receiving the goods. Different lead times measure different stretches of that journey.
What are the types of lead time?
Common ones are pre-processing, supplier, transit, post-processing, total procurement, manufacturing, cumulative and customer order lead time.
How do you calculate supplier lead time?
For each order, subtract the PO date from the goods receipt (or ship) date, then look at the average and spread across many orders.
What is the difference between lead time and cycle time?
Lead time includes waiting before work starts, from request to result. Cycle time usually covers only the active processing once work begins.
Why does lead time variability matter?
Safety stock grows with the spread of lead time, not only its average. An unreliable supplier can need far more buffer than a slow but steady one.