Canal and strait closures: the ships reroute, the lead times don't

When a chokepoint closes, carriers find another way within days. The planning system can take months to notice.

OpEx 3Ws10 min readUpdated 19 Nov 2026Facts checked Nov 2026

The short answer

  • When a canal or strait closes or turns unsafe, carriers reroute. Around Africa instead of through Suez, delivery times rose by ten days or more on average, the IMF found in 2024.
  • Carriers add war-risk, diversion or emergency surcharges per container, and more of your stock is on the water at any moment.
  • The quiet damage is in planning: if lead times in the item master stay old, reorder points fire late and shelves empty before the slower ships arrive.
  • The return is a second shock. As services swing back through Suez from late 2026, transit shortens, arrivals bunch and diversion surcharges come into question.
Update · 19 Nov 2026 (The 3Ws Weekly, Issue 01). Maersk and Hapag-Lloyd say their Gemini AE1, AE2 and AE3 services return to the Suez route, with first sailings in December and January, if the region stays stable (FreightWaves). Ships back on Suez since June freed over 500,000 TEU of capacity, now taken up by Far East–Middle East trades (Zencargo). A new question for your files: when the route shortens again, who updates the lead times in your planning system?
A STORY · NAMES AND NUMBERS INVENTED

The reorder point fired on a Tuesday, exactly as designed. The system read the lead time field, 38 days, and placed the order. The field had been set years earlier, when the ships still went through the canal.

At the forwarder, a new line had appeared on every invoice for the lane: an emergency surcharge per container. In the warehouse, in-transit stock for the same items had crept up for three months while stock on hand drifted down.

On day 41 the shelf was empty. The ship was still off Africa.

What happens when a canal or strait closes?

A chokepoint is a narrow passage that a large share of world shipping has to use. When one closes, through war, drought or a grounded ship, there is rarely a quick alternative by sea.

ChokepointWhat closed itWhat carriers didWhat it added
Suez and the Red SeaAttacks on ships, from Nov 2023Sailed around the Cape of Good HopeTen days or more on average; surcharges
Panama CanalDrought, 2023–24Fewer daily slots, lighter loadsQueues and slot auctions
Strait of HormuzWar, from late Feb 2026Stopped Gulf bookings; land bridgesWar-risk surcharges; trucking legs
From a closed strait to an empty shelfClosurea canal or strait closes orturns unsafeReroutelonger route, more days andmore stock at seaOld lead timethe item master still holdsthe pre-closure daysLate reorderreorder points fire too latefor the new transitStockoutshelves empty before theslower ships arriveAir to coverpremium freight fills the gap
A shipping event becomes a planning error. The closure is outside anyone's control; the stale lead time is inside the house.

Surcharges and the lead-time trap

Surcharges are visible: a new line, a price per box. What matters is when they start and stop, and whether the contract names a trigger. A surcharge with no end date tends to outlive the closure.

The lead time is invisible: one field per item, trusted by the planning system. Safety stock built on the old transit cannot absorb two extra weeks. When the route reopens the error flips, and too much stock lands at once; hubs feel it first, as in missed transshipment connections.

One reorder, two lead timesInvented example · days from the purchase orderstock on hand covers demandshelf empty01020304050daysreorder firesplanned arrivalshelf emptyair freight bookedship arrivesPlanned for 38 days; the Cape route took 50. Three days of safety stock could not cover twelve.
Twelve days nobody planned for. Nothing was ordered late by a person; the order was late because a field was old.

The signs already in your files

One late ship is noise. A diversion that has reached your planning shows in several reports at once:

  • Your tracking shows transit days on the lane up by a similar amount across many shipments, by a different route.
  • Your freight invoices carry war-risk, diversion, emergency or contingency surcharges for the lane.
  • Your item master still holds the old lead time for items sourced on that lane.
  • Your stock reports show in-transit quantity up and on-hand quantity down for the same items.

What it costs, told honestly

Invented numbers for one Asia–Europe lane over a quarter, each pool against its own total:

PoolTotalOf whichShare
Goods on the lane, in transit and on hand3,600,0001,220,000 of extra goods value on the water from longer transit34%
Freight billed on the lane410,00073,800: 52,000 diversion and war-risk surcharges plus 21,800 air freight for gaps18%
Items sourced on the lane212 itemsitems still planned on the pre-closure lead time61 of 212
Open customer orders for those items90 ordersorders hit by a stockout14 of 90
One lane, four poolsInvented numbers · never added togetherGoods on the lane34%extra value on the waterFreight on the lane18%surcharges plus air freightItems on the lane61 of 212planned on an old lead timeCustomer orders14 of 90hit by a stockoutFreight against freight, stock against stock. One dollar is counted once.
Four pools, four totals. The items line costs nothing itself; it is why the other three move.

How the world answers

Three chokepoints closed in three years, by war, by drought and by war again. Each left a different bill.

Egypt and the Red Sea The long way round · 2023–2026

Attacks on ships in the Red Sea began on 18 November 2023. On 5 January 2024 Maersk said its ships would sail around the Cape of Good Hope for the foreseeable future, after adding a transit disruption surcharge from late December of $200 to $400 per dry box from the Far East. By February, UNCTAD counted weekly container-ship transits of Suez down 67%.

Suez Canal revenue fell from $10.25 billion in 2023 to about $3.99 billion in 2024. Maersk tested the route again in early 2026 but withdrew when war with Iran broke out at the end of February; carriers came back service by service from July.

Last effect: on 16 November 2026 Maersk and Hapag-Lloyd said three more Asia–Europe services would return to Suez between 4 December and 14 January 2027, if the Red Sea stays stable. In August 2026, ship numbers on the route were still about 65% below August 2023.

Panama A canal short of water · 2023–2026

Drought lowered Gatun Lake, which feeds the Panama Canal's locks. In 2023 the canal cut the maximum draft for its largest locks from 50 feet to 43 feet and reduced daily slots: for January 2024 it set 24 transits a day, against 36 normally. In November 2023 one shipper paid about $3.98 million at auction for a slot.

Last effect: the 50-foot draft returned on 15 August 2024 and 36 daily slots on 1 September; the drought had cost about 2,700 transits. A new reservoir at Río Indio, about $1.5 billion in all, is due to start construction in 2028.

The Gulf A strait at war · 2026

After US and Israeli strikes on Iran and Iranian attacks across the region, carriers stopped crossing the Strait of Hormuz. Maersk suspended crossings on 1 March 2026. Hapag-Lloyd added a war risk surcharge of $1,500 per TEU from 2 March and stopped bookings to several Gulf states on 4 March. Maersk routed cargo through ports in Saudi Arabia, Oman and the UAE and trucked it on. From mid-July to late August, Al Jazeera reported, the strait averaged about five transits a day, against about 100 before the war.

Last effect: October 2026 saw 750 crossings, the most since July, but the IMO secretary-general cited about 30 attacks that month and advised ships to stay away.

Questions to ask before you act

  1. When were planning lead times last updated for those items, and by whom?
  2. Does the contract say when diversion or war-risk surcharges start and stop?
  3. When the route reopens, which surcharges end, and who checks that they do?
  4. Is the extra stock on the water in the cash forecast?

Frequently asked questions

How much longer is the Cape of Good Hope route than Suez?

For Asia–Europe services, the IMF reported in 2024 that delivery times rose by ten days or more on average; the exact figure depends on ports and speed.

What is a war risk surcharge on a container?

A per-container charge for sailing in or near a conflict area, to cover higher insurance and security costs. Amounts and start dates are set in carrier notices.

Are container ships back in the Suez Canal?

Partly. Through 2026 carriers moved services back one by one, with more planned for December 2026 and January 2027, each subject to Red Sea security.

Should lead times be changed during a diversion?

Planners commonly update lane lead times and safety stock once a diversion looks lasting, and reverse them when the route reopens.