MRP (material requirements planning): working backwards from the build date

MRP takes a production plan and calculates every part to order, how many and when. The arithmetic is simple; the trouble is that it trusts every number it is given.

OpEx 3Ws6 min readUpdated 19 Nov 2026Facts checked Nov 2026

The short answer

  • Material requirements planning (MRP) calculates which components and materials to order or make, in what quantity and by what date, to meet a production plan.
  • It uses three inputs: the master production schedule (what to build, when), the bill of materials (what goes into each product) and inventory records (stock on hand and on order).
  • It explodes the schedule through the bill of materials, nets the result against stock, and offsets each need by its lead time to set the order date.
  • MRP is only as good as its data. A wrong lead time, unit of measure or stock count produces confident, wrong orders.

What is MRP?

Material requirements planning is a method, now built into almost every ERP system, for planning the purchase and production of the parts that go into a finished product. It answers three questions for every component: how many are needed, when, and how many must be ordered once existing stock is counted.

The key idea is dependent demand. Customers create demand for finished products; that demand is forecast. The demand for the parts inside them is not forecast at all: it is calculated. If 400 lamps are scheduled and each needs two hinges, the hinge requirement is 800, with no guessing.

Before MRP, many plants ordered parts by reorder point, topping up when stock fell to a set level. MRP spread as computers made the calculation practical across thousands of parts. Its later extension, MRP II (manufacturing resource planning), added capacity, scheduling and costing.

How MRP works: explode, net, offset

From build plan to purchase orderMaster schedulefinished items, quantities anddue weeksBOM explosioneach item broken into itsparts and quantitiesNet against stockon hand and on ordersubtracted; bad counts hideLead-time offsetneed date moved back by thelead timePlanned orderssuggested buys and builds forplanners to release
Backwards from the due date. MRP starts with the finished build date and works back through every level of the product.

For each component and each week, the calculation is written plainly as:

Net requirement = gross requirement − stock on hand − scheduled receipts + safety stock (never below zero). Order release date = date needed − lead time.

The net requirement is then rounded by the item's lot-sizing rule: exact quantity, a fixed batch, a minimum order quantity or a pack multiple. The result is a planned order. Planners review it, release it as a purchase or work order, and MRP also sends reschedule messages when an open order is now too early or too late.

MRP vs reorder point

REORDER PTMRPVSwaits for stock to falllooks back at past usagecalculates from the build planlooks ahead at dependent demandIndependent vs dependent demand
Looking back, looking ahead. Reorder points suit steady, independent items; MRP suits parts whose need follows a schedule.

A reorder point works well for items with steady, independent demand: spare parts, consumables, goods sold as they are. It struggles with parts used in lumpy batches, because average usage says nothing about the big run scheduled for week 12. MRP sees that run coming. Many companies use both: MRP for production parts, reorder points for the rest.

A worked example

Invented numbers. A desk lamp is built from 1 base, 1 arm and 2 hinges. The master schedule asks for 400 lamps in week 8. Assembly takes one week, so parts are needed in week 7. Hinges come from a supplier with a three-week lead time and a minimum order of 500.

HingesQuantity
Gross requirement, week 7 (400 × 2)800
Stock on hand150
Scheduled receipt, arriving week 5200
Net requirement450
Planned order after the 500 minimum500
Order release (week 7 − 3 weeks)week 4

Now suppose the bill of materials lists 2 pairs of hinges where it means 2 pieces. The gross requirement doubles to 1,600 and MRP orders 1,250, which is 800 more than the lamps need. Or suppose 120 of the 150 on hand were scrapped but never booked out. The real net need is 570, MRP orders 500, and the gap of 70 appears on the assembly line in week 7. Neither error is in the arithmetic; both are in the data it was fed.

Common MRP mistakes

Stock that is not thereMRP nets against the system count, not the shelf. A count that is too high delays the order until it is too late. See phantom inventory.
Units that do not matchThe bill of materials says pieces, the supplier sells packs, the receipt is booked in boxes. One mismatch multiplies through every order, as told in unit of measure errors.
Lead times from years agoMRP treats each lead time as fact. When the real lead time has grown, every order is released late, and the shortfall is rescued with expediting.

Questions to ask before you act

  1. How accurate are the stock records MRP nets against, and when were they last counted?
  2. Do the bill of materials, the purchase unit and the stock unit use the same unit of measure?
  3. When were supplier lead times in the item master last compared with actual deliveries?
  4. Are reschedule messages acted on, or ignored because there are too many?
  5. Is the master schedule stable enough near term, or does it change after orders are released?

Frequently asked questions

What is MRP in supply chain?

MRP, or material requirements planning, is a method that calculates which parts and materials to buy or make, how many and when, from the production schedule, the bill of materials and inventory records.

What are the three inputs of MRP?

The master production schedule, the bill of materials and the inventory records, which include stock on hand and orders already placed.

What is the difference between MRP and MRP II?

MRP plans materials. MRP II, manufacturing resource planning, extends it to machine and labour capacity, detailed scheduling and cost data for finance.

What is the difference between MRP and ERP?

MRP is one planning function. An ERP system is the wider software suite that runs finance, sales, purchasing, inventory and production, and usually includes an MRP module.

What is gross-to-net in MRP?

It is the step that subtracts stock on hand and scheduled receipts from the gross requirement to find the net quantity that still needs to be ordered or made.