The short answer
- A supplier scorecard is a regular report that rates a supplier on a small set of agreed KPIs (key performance indicators).
- The usual groups are quality (defects, returns), delivery (on time, in full, lead time), cost (price, total cost) and service (responsiveness, documents, flexibility).
- Each KPI has a formula, a target and a weight; the weighted results add up to an overall score, often shown as a grade or a traffic light.
- Scorecards feed supplier reviews, development plans, sourcing decisions and the total cost of ownership of each supplier.
What is a supplier scorecard?
A supplier scorecard is the working tool of supplier performance management: the ongoing process of checking that approved suppliers keep delivering what was agreed. Approval is the entry ticket; the scorecard checks the supplier keeps earning its place.
Most scorecards are monthly or quarterly, built from data already in the company's systems: purchase orders, goods receipts, inspection results, returns and invoices. Quality and delivery appear on almost every scorecard; cost, responsiveness, sustainability and risk are added as the relationship matters more.
Common supplier KPIs and how they are calculated
| KPI | Plain formula | What it shows |
|---|---|---|
| On-time delivery | Lines received on time ÷ lines due in the period | Reliability of dates |
| In full | Lines received at full quantity ÷ lines received | Reliability of quantities |
| On time in full (OTIF) | Lines both on time and in full ÷ lines due | Both at once; see OTIF |
| Defect rate (ppm) | Rejected units ÷ units received × 1,000,000 | Quality in parts per million |
| Lead time | Receipt date − order date, as an average and a spread | Speed and its stability |
| Price variance | (Invoice price − agreed price) ÷ agreed price | Whether contract prices hold |
| Responsiveness | Days to answer a quote, a change or a complaint | Service and flexibility |
The key definition is the date that counts as on time: the date the supplier confirmed, the date the buyer requested, or the dock date. Each gives a different score.
A weighted score combines them. For example: overall score = 40% × quality score + 40% × delivery score + 20% × cost score, where each score is the KPI result turned into points against its target.
A worked example
Invented numbers. A buyer reviews three resin suppliers for one quarter, with weights of 40% delivery, 40% quality and 20% cost.
East has the lowest price, so it scores full cost points. But its defect rate is 2,400 ppm against a 500 ppm target, and its late lines triggered air freight. Its weighted score comes out at 71, against 89 for North. Without the scorecard, East's low price would have won it more volume at the next award.
Common scorecard mistakes
Questions to ask before you act
- Which date counts as on time: requested, confirmed or dock date?
- Were the weights agreed before the results were calculated?
- Are the receipt and inspection data behind the score checked?
- Does each supplier see its own scorecard, and what happens after a red score?
Frequently asked questions
What is a supplier scorecard?
A regular report that rates a supplier on agreed KPIs such as on-time delivery, defect rate, price compliance and responsiveness, usually with weights and an overall score.
What KPIs should be on a supplier scorecard?
Most include on-time delivery, in-full or OTIF, defect rate, lead time and price variance. Responsiveness, sustainability and risk measures are often added for key suppliers.
How do you calculate supplier on-time delivery?
Divide the order lines received on time by the lines due in the period. The result depends on which date counts as on time, so that date is part of the definition.
What does PPM mean for suppliers?
Parts per million: rejected units divided by units received, multiplied by 1,000,000. 500 ppm means 5 rejects in every 10,000 units.
How often should suppliers be scored?
Monthly or quarterly is common for active suppliers, with a fuller review, often yearly, for key suppliers and for re-approval.