The short answer
- An RFI (request for information) gathers facts about suppliers and the market. It is a scouting step, and the answers bind nobody.
- An RFP (request for proposal) describes a need and asks suppliers to propose a solution, a price and a plan. It suits work where the answer is not yet fixed.
- An RFQ (request for quotation) sends a fixed specification and asks for a price, quantity, lead time and terms. It suits standard items where price is the main difference.
- They often run in order: RFI, then RFP, then RFQ, ending in a contract or a purchase order. Small buys may skip straight to an RFQ.
What are RFI, RFP and RFQ?
All three are solicitations: formal messages a buyer sends to suppliers asking for an answer in a set format by a set date. The letters tell the supplier what kind of answer is wanted.
- RFI: "Tell us who you are and what you can do." Capabilities, locations, certifications, capacity, references. Used to learn a market and build a shortlist.
- RFP: "Here is our problem. How would you solve it, and at what price?" Used for services, systems and anything where suppliers may propose different approaches, such as a warehouse operation, a freight tender or a software tool.
- RFQ: "Here is exactly what we need. What is your price?" Used for parts, materials and services with a clear specification, so every quote prices the same thing.
Some organisations use other names. A request for tender (RFT) or invitation to bid (ITB) is close to an RFQ, often in the public sector. Many companies also say "RFQ" for any request that ends in a price.
RFP vs RFQ: which one fits?
The test is simple: can the buyer write the specification today? If yes, an RFQ lets suppliers compete on price, lead time and terms. If no, an RFP lets suppliers show how they would meet the need, and the buyer learns from the answers.
| RFI | RFP | RFQ | |
|---|---|---|---|
| Main question | Who can do this? | How would you do it? | What does it cost? |
| Specification | Loose or none | Need and outcomes | Fixed and detailed |
| How answers are compared | Fit for a shortlist | Weighted criteria | Mainly price and terms |
| Typical use | New market or category | Services, systems, 3PL, freight tenders | Parts, materials, repeat buys |
| Binding? | No | Depends on the wording | Depends on the wording and the law |
Whether a supplier's answer is a binding offer depends on its wording and on the law that applies. In US federal buying, for example, FAR 13.004 treats a quotation as not an offer; the government's order is the offer.
What goes into a good request
In US federal buying, FAR 15.203 lists the minimum a competitive RFP describes: the requirement, the expected contract terms, what the proposal must contain, and the evaluation factors with their relative weight. Private buyers are not bound by the FAR, but the same four parts make any request easier to answer fairly.
For an RFQ in physical goods, a few fields decide whether quotes can be compared at all: the exact part or drawing revision, quantity and delivery schedule, the Incoterms rule and named place, currency, payment terms, and how long the price stays valid. Two quotes on different Incoterms or currencies are two different prices, even when the figures look alike.
A worked example
Invented numbers. A medical device maker needs a new supplier for machined aluminium housings. It sends an RFI to 14 machine shops asking about capacity, certifications and export experience. Six answer well.
Because the housing design is fixed, it skips the RFP and sends an RFQ to the six: 4,000 units a year, drawing revision C, FCA named place, US dollars, net 45, prices valid 90 days. Quotes come back between 17.80 and 23.40 dollars a unit.
The lowest quote turns out to be EXW and excludes anodising. Rebuilt on the same basis, it becomes 21.10 dollars, and the second-lowest shop wins at 19.60. The buyer then compares the finalists on more than price, as described in total cost of ownership.
Common RFQ and RFP mistakes
Questions to ask before you act
- Can the specification be written down today, or are suppliers expected to shape it?
- Are the evaluation criteria and their weights stated in the request itself?
- Do all quotes use the same Incoterms rule, currency, quantity and payment terms?
- How long is each price valid, and does the approval process fit inside that window?
- Is the request worded so that the answers are, or are not, binding offers?
Frequently asked questions
What is the difference between an RFP and an RFQ?
An RFP describes a need and asks suppliers to propose a solution and price. An RFQ gives a fixed specification and asks only for price, lead time and terms.
What comes first, RFI or RFP?
Usually the RFI. It gathers information and builds a shortlist, and the RFP or RFQ follows for the suppliers that fit.
Is a quotation a binding offer?
It depends on its wording and the governing law. Some quotes are stated as firm offers; under US federal rules (FAR 13.004) a quotation is not an offer, and the buyer's order is the offer.
Is an RFQ the same as a tender?
They are close. A tender or invitation to bid usually also asks for a firm price against a fixed specification, often with formal public-sector rules on opening and award.
Does every purchase need an RFQ?
No. Many companies set spend thresholds or use existing contracts and catalogues for routine buys, and keep RFQs for new parts, new suppliers or larger amounts.
Read next
Sources
- FAR Subpart 15.2: Solicitation and receipt of proposals and information
- FAR 13.004: Legal effect of quotations
- Wikipedia: Request for quotation
- Wikipedia: Request for proposal
- Wikipedia: Request for information
Sources opened and checked Nov 2026.