Purchase order (PO): the buyer's promise, in writing, before anything ships

A purchase order is the buyer's formal offer to buy. Once accepted it can be a contract, and every later document is checked against it. Here is what it does, what it must say, and where it quietly fails.

OpEx 3Ws7 min readUpdated 19 Nov 2026Facts checked Nov 2026

The short answer

  • A purchase order (PO) is a document a buyer sends a supplier stating what it wants to buy: items, quantities, prices, delivery date, place and payment terms.
  • Legally it is usually an offer. Once the supplier accepts it, by confirming or by shipping, it can form a binding contract.
  • When the PO and the supplier's acknowledgement carry different terms, the conflict is called the battle of the forms. In US sales of goods, UCC § 2-207 decides which terms survive.
  • Inside the company, the PO commits budget and becomes the reference that the goods receipt and invoice are matched against before payment.

What is a purchase order?

A purchase order is a buyer-issued document that authorises a purchase and tells the supplier exactly what is being bought and on what terms. It is usually created in an ERP or purchasing system, numbered, approved according to spending limits, and sent by email, portal or EDI.

It does three jobs at once. To the supplier, it is an order to fulfil. To the company, it is a spending commitment approved in advance. To accounts payable, it is the yardstick for the later three-way match of order, receipt and invoice.

The life of a purchase orderRequisitionsomeone inside asks to buy;budget is checkedPO issuedapproved, numbered and sent:the buyer's offerSupplier acceptsconfirms, or simply ships: acontract can formGoods receivedreceipt posted against the POlineInvoice matchedprice and terms differ fromthe PO: held
One number, end to end. The PO number links the request, the contract, the receipt and the invoice.

Usually a PO is an offer. It becomes a contract when the supplier accepts it: by signing an acknowledgement, by confirming in writing, or by shipping the goods. Until then, the buyer can normally withdraw it. Many POs state which form of acceptance counts.

Trouble starts when the supplier accepts on its own form, with its own terms. In the US, sales of goods fall under the Uniform Commercial Code. UCC § 2-207 says a reply that accepts can still create a contract even if it adds terms. Between merchants, the added terms become part of it unless the offer limited acceptance to its own terms, the additions materially alter the deal, or the buyer objects in time. Where both sides act as if a deal exists despite conflicting paper, the contract is what the documents agree on, plus the Code's default rules.

Under UCC § 2-201, a contract for the sale of goods for 500 dollars or more generally needs a signed writing to be enforceable, though between merchants a written confirmation not objected to within 10 days can be enough. International sales between businesses in many countries fall instead under the UN Convention on Contracts for the International Sale of Goods (CISG), adopted in 1980 and in force since 1988, which has its own rules on offer and acceptance. Which law applies depends on the parties and the contract, so this is a description, not legal advice.

What should be on a purchase order

FieldWhy it matters later
PO number and dateThe key every receipt, invoice and query refers to
Supplier name and IDPays the right legal entity, not a duplicate vendor record
Item, part number, descriptionWhat the receipt and inspection compare against
Quantity and unit of measureEaches vs cases errors start here
Unit price and currencyThe price the invoice must match
Incoterms rule and named placeWho pays freight and where risk passes
Delivery date and ship-to addressThe promise the supplier is measured on
Payment termsNet 30, 2/10 net 30: the clock for paying
Terms and conditions referenceWhich standard terms govern, and how acceptance works

Add HS code and country of origin when the goods cross a border; customs and landed cost depend on them.

A standard PO covers a one-off purchase. A blanket PO sets prices and a total value for repeated buys over a period, with releases for each delivery. A contract PO references a separate framework agreement without listing items.

Purchase order vs requisition vs invoice

A purchase requisition is an internal request to buy; it never leaves the company. The PO is the external order built from it. A sales order is the supplier's internal record of the same deal. The invoice is the supplier's bill after delivery, and a proforma invoice may come before it.

REQUISITIONPOVSINTERNAL: a request to buybinds nobody outsideEXTERNAL: an offer to buybinding once acceptedThe request asks; the order commits
Inside vs. outside. A requisition stays in the building; a purchase order is a promise made to a supplier.

A worked example

Invented numbers. A food maker issues PO 45118 for 2,000 kg of cocoa butter at 7.80 euros per kg, FCA Antwerp, net 60. The supplier replies with its acknowledgement: same quantity and price, but payment net 30 and a 1.5% monthly late fee.

Nobody reads the acknowledgement. Goods ship and arrive. The invoice says net 30. Which term runs depends on the law that applies and on whether the PO limited acceptance to its own terms, the conflict described in payment terms that differ from the PO. A PO clause limiting acceptance to its own terms, and a buyer who reads acknowledgements, make it far more likely the original 15,600 euro deal on net 60 is the one that holds.

Common purchase order mistakes

The after-the-fact PORaising the PO once the invoice arrives turns the control into paperwork. The price on the PO is then simply whatever was billed, the pattern behind invoice price vs PO.
Unread acknowledgementsSuppliers often confirm with different terms, currency or dates. If nobody compares them, the supplier's version can become the deal.
Vague units and places"100 boxes" or "FOB China" leaves room for two readings. Units and named places are where later disputes start, as in case vs each.

Questions to ask before you act

  1. Is the PO raised before the supplier is asked to ship, every time?
  2. Does the PO say how the supplier accepts, and that our terms prevail?
  3. Who compares the supplier's acknowledgement with the PO, and how quickly?
  4. Are unit of measure, currency, Incoterms rule and named place written on every line that needs them?

Frequently asked questions

What is a purchase order in simple terms?

It is a buyer's written order to a supplier listing what it wants to buy, how many, at what price, when and where, and on what payment terms.

Is a purchase order a legally binding contract?

Usually it is an offer that becomes binding when the supplier accepts it, by confirming or by shipping. The exact rules depend on the law that governs the sale.

What is the difference between a purchase order and an invoice?

The buyer sends the purchase order before delivery to order goods. The supplier sends the invoice after delivery to ask for payment, and it is checked against the PO.

What is the difference between a purchase requisition and a purchase order?

A requisition is an internal request to buy, approved inside the company. A purchase order is the external document sent to the supplier.

What is a blanket purchase order?

It is a PO that covers repeated purchases of the same items over a period, at agreed prices and up to a total value, with separate releases for each delivery.