The short answer
- A price variance is the gap between the unit price on the supplier's invoice and the unit price on your purchase order (PO) for the same line.
- The usual causes are plain: an old price list, a surcharge nobody agreed, or a slip in currency or price unit (per 1 against per 100).
- A three-way match compares invoice, PO and receipt before payment; a wide tolerance lets a real price change pass as rounding.
- On imported goods the price paid is normally the customs value, so duty follows the higher price, and the gap ends up in purchase price variance (PPV), reported by account rather than by supplier.
At the quarter-end review, the controller pointed at one line: purchase price variance on a small brass fitting, up for the third quarter running. The buyer shrugged. Brass was up everywhere.
Two floors down, an accounts payable clerk remembered the fitting. Its invoices had landed a little above tolerance for months, and each time someone clicked approve: the receipt matched and the supplier was reliable. At the customs broker, entries for the same fitting declared the invoice price, as they should, and duty was paid on it.
The PO said 4.20. The supplier's system still said 4.62, the price from before the last negotiation.
Why does an invoice price differ from the PO?
Most gaps are not bad faith. Two systems stopped agreeing: the buyer's ERP holds the negotiated price, the supplier's billing system holds the last price it was given.
Where the price gap goes after payment
Once paid, the gap leaves accounts payable and travels through three more places, each harder to see.
The customs step matters because the starting point for customs value in most countries is the transaction value: the price actually paid or payable. If a credit note later lowers the price, getting back the duty on the difference needs a post-entry correction or refund claim, under rules and deadlines that vary by country. Import VAT is usually recoverable for a registered importer, so it costs timing rather than money.
The signs already in your files
A price change can be legitimate. It becomes a leak when two different records disagree with the PO and nobody went back to the supplier:
- Your commercial invoices show a unit price above the PO price on the same line, after putting both in the same currency and price unit.
- Your AP ledger shows those invoices paid in full, with no debit note and no short payment.
- Your customs entries declare the invoice price, not the PO price.
- Your general ledger posts purchase price variance on the same item in the same period.
What it costs, told honestly
Each pool is measured against its own total, never added together. Invented numbers for one fitting over one quarter:
| Pool | Total | Of which | Share |
|---|---|---|---|
| Supplier payments | 55,440 paid on these PO lines | 5,040 above the PO price (12,000 units × 0.42) | 9.1% |
| Duty & taxes | 3,604 duty on the entries | 328 duty on the price gap | 9.1% |
| Goods & stock | 61,900 landed value of the receipts | 5,368 posted to purchase price variance | 8.7% |
| Recovery | 5,040 variance paid | 5,040 not yet credited | 100% |
The landed value already holds the supplier and duty amounts, so the pools are never summed. The last line matters most: nothing has been asked back yet.
How the world answers
Three public records show where the gap ends: credited back, found too late, or kept in the customs value.
United States Credited back after an audit · 2014–2017
The US Defense Department's Inspector General reported in 2014 that the Defense Logistics Agency had paid too much for Humvee repair parts. A 2016 follow-up found the agency had reconciled billing for parts needing a unit-of-issue conversion, February 2009 to September 2013, and issued $1.62 million in credit memos against the manufacturer.
A 2017 audit of engine spare parts found 82 delivery orders placed with incorrect unit prices; uncorrected, 45 of them would have cost $407,317 more than necessary.
Last effect: the 2016 follow-up found no further Humvee-part overpayments after monthly reconciliations to October 2015; on the engine parts, 25 orders were modified and $37,323 of refunds were still unrequested in 2017.
India Found by the state auditor · 2018
India's Comptroller and Auditor General, reporting on the year to March 2018, found that Nagaland's Power Department paid INR 22.50 crore more than due to contractors and suppliers on six projects. On one substation it paid INR 31.81 crore for items whose suppliers' own tax invoices showed INR 8.62 crore before taxes and freight.
Last effect: the published account of the audit records no response or recovery from the department.
Germany and the EU The duty does not follow the price down · 2017–2022
A German subsidiary of a Japanese group had its import prices cut retroactively under a transfer-pricing agreement and asked for duty back. In December 2017 the EU Court of Justice (C-529/16, Hamamatsu) held that a transaction value built on a lump-sum adjustment made after the period, whose direction was unknown at import, cannot be used. A related-party case, but the lesson travels: customs keeps the price of the day of import.
Last effect: Germany's Federal Fiscal Court dismissed the appeal on 17 May 2022 and denied the refund, adding that such retroactive adjustments change the final customs value in neither direction.
Questions to ask before you act
- Was a new price agreed before these goods shipped, and is it on a PO amendment or only in an email?
- What price tolerance does the three-way match use, and when was it last changed?
- Are the PO and the invoice priced in the same unit and currency for this item?
- Has the supplier been asked for a credit, and is a debit note open?
- If a credit arrives, which customs entries carried the higher value, and is a correction still possible there?
Frequently asked questions
What is an invoice price variance?
It is the difference between the unit price the supplier invoices and the unit price on your purchase order for the same line, multiplied by the quantity invoiced.
Does customs duty go down if the supplier later issues a credit note?
Not automatically. The customs value is normally the price paid or payable at import; recovering duty after a price reduction needs a correction or refund claim under each country's rules and deadlines.
What is purchase price variance (PPV)?
PPV is the difference between the standard or expected cost of an item and the price actually paid. It shows that something changed, not who changed it, unless reported by supplier and item.
Read next
Sources
- DoD IG: DLA Land and Maritime paid too much for HMMWV repair parts (DODIG-2014-054)
- DoD IG: follow-up audit on HMMWV parts (DODIG-2016-083)
- Defense Daily: AM General credits DLA with $1.62 million
- DoD IG: F402 engine spare parts pricing errors (DODIG-2017-050)
- Eastern Mirror: CAG finds Nagaland Power Department paid INR 22 crore in excess
- eClear: German Federal Fiscal Court rejects appeal in Hamamatsu case
Sources opened and checked Nov 2026.