Over-shipment: how 600 units nobody ordered get received, matched and paid

The receipt agrees with the invoice, so the match passes. The one document that disagrees, the purchase order, is often not part of the test. Here is the path, the cost and the questions.

OpEx 3Ws7 min readUpdated 19 Nov 2026Facts checked Nov 2026

The short answer

  • An over-shipment is a delivery above the quantity on the purchase order (PO), beyond any agreed over-delivery tolerance.
  • If the warehouse books the full quantity, the receipt and the invoice agree, and a three-way match that compares invoice with receipt passes and pays the excess.
  • The extra units become owned stock: cash tied up, turns down, space used, and on imported goods duty already paid.
  • Sending the excess back costs return freight, and the import duty comes back only under returned-goods rules that vary by country.
A STORY · NAMES AND NUMBERS INVENTED

The forklift driver needed the overflow aisle for a project shipment and found it full of grey cartons: a pump seal kit, three pallets of it, labelled with a receipt from five weeks back.

In planning, the seal kit showed 41 days of cover against a target of 30. The planner assumed a forecast had gone wrong and cut the next two orders. In payables, the supplier's invoice for 2,600 kits had matched the receipt for 2,600 kits on the first pass and was paid on its due date.

The purchase order, in a folder nobody opened that week, said 2,000.

How does an over-shipment get paid?

Suppliers over-ship for ordinary reasons: a full production batch, a full pallet layer, a minimum run, or stock they would rather hold on your books than theirs. The control that should catch it sits at the dock, and the dock is busy.

Where the extra 600 units slip throughDelivery2,600 kits arrive on a PO for2,000Goods receiptDock counts and books all2,600Three-way matchInvoice 2,600 = receipt 2,600:passesPaymentExcess paid at the PO unitpriceStock on hand41 days of cover against atarget of 30
The match agreed with itself. Once the receipt carries the excess, the invoice and the receipt are two witnesses telling the same wrong story.

The receipt is the gate. Once it is posted at the full quantity, the system no longer records that 600 units were never asked for, and recovery depends on the supplier agreeing to credit or take them back.

What contracts usually say about excess quantities

Many purchase terms set an over-delivery tolerance (often a few percent, to allow for batch sizes) and say what happens above it. The US federal clause on excess quantities is a clear public example.

Excess beyond the allowed variationWhat the buyer may do under FAR 52.211-17
Worth $250 or lessKeep it without paying; the contractor gives up its claim to the items
Worth more than $250Return it at the contractor's expense, or keep it and pay the contract unit price

US Federal Acquisition Regulation clause 52.211-17. Private contracts set their own terms; check yours.

The point is the default, not the dollar line: excess is the supplier's choice, so undoing it can be the supplier's cost too, if the terms say so and someone noticed in time.

The signs already in your files

One generous delivery is noise. It becomes a pattern when separate records agree that more arrived than was ordered and it was paid:

  • Your receiving log shows a quantity above the PO quantity, beyond the tolerance, on a PO line.
  • Your commercial invoice bills the same higher quantity.
  • Your AP ledger shows the invoice paid in full, with no debit note for the excess.
  • Your stock snapshot shows the item above its planned maximum or days of cover right after the receipt.
Watch the reverse too: a receipt that does not match the PO and shipping notice can be a short delivery. And when the quantity is right but the price is not, see invoice price above the PO.

What it costs, told honestly

Each pool against its own total, never summed. Invented numbers for one PO line of 2,000 kits at 18.50, with a 2% over-delivery tolerance:

PoolTotalOf whichShare
Supplier payments48,100 paid on the PO line10,360 for 560 kits above PO quantity plus tolerance21.5%
Goods & stock62,900 on hand for the item10,360 of unplanned stock16.5%
Cash timing30 days of cover planned11 days added by the excess11 of 30 days
Freight2,300 inbound freight on the order640 to send the excess back28%
Duty & taxes2,405 duty on the entry518 duty on the excess units21.5%

Cash timing is counted in days, not money. If the kits are returned, the 518 of duty comes back only if the import country's returned-goods relief applies.

How the world answers

No public record of a pure over-shipment paid in full surfaced in our search. The two closest audits show the same mechanism: a receiving record that agreed with the bill, not with the order.

Philippines The inspection report copied the PO · 2022

The Commission on Audit's 2022 report on Iloilo province found that its General Services Office had accepted and paid for farm inputs, in a purchase of about P3.378 million, where two items did not match the purchase order: a different pesticide was delivered for one, and 20-gram packets instead of 35-gram packets for another.

The acceptance and inspection report listed the items as written on the PO rather than as delivered. The office said the inspector had taken the short-weight packets because the supplier offered extra ones.

Last effect: the provincial accountant sent the supplier a demand letter to refund the price difference; auditors also recommended delivery of extra packets to make up the missing weight, and the office promised staff training in 2023 and inspection teams to share accountability.

United States Billed beyond the work order · 2016–2019

The North Carolina State Auditor reported in October 2019 that a parts vendor managing inventory for the Town of Chapel Hill's fleet had billed at least $210,035 improperly between January 2016 and March 2017, including parts added to invoices beyond those on work orders, parts that did not fit town vehicles, and duplicate invoices.

The errors went unseen because the town's work-order system did not connect with the vendor's invoices and invoices were not adequately reviewed.

Last effect: the vendor had reimbursed $134,112; the town introduced new parts accounting procedures in January 2019, and the auditor recommended seeking repayment for unused parts.

Questions to ask before you act

  1. Is there an agreed over-delivery tolerance with this supplier, and is it written on the PO?
  2. Does the dock see the PO quantity when it counts, or only the shipping notice?
  3. Was the excess asked for by a buyer, by phone or email, after the PO was issued?
  4. Who pays return freight under the PO terms, and has the supplier been asked?
  5. Will the excess be used within the planning horizon, or is it heading for the slow-moving list?
Book what arrivedLEAKINGinvoice and receipt agree, match passesexcess paid, then hidden in the planCount against the POCLEANexcess held for the buyer's decisiondebit note or return before payment
Same dock, two habits. The delivery is identical; what changes is whether the PO quantity is in the room when the count is booked.

Frequently asked questions

What happens if a supplier ships more than ordered?

It depends on the purchase terms. Usually the buyer can refuse or return the excess at the supplier's cost, keep it and pay for it, or keep it under a stated tolerance.

What is an over-delivery tolerance?

A percentage or quantity above the PO quantity that the buyer agrees to accept and pay for, usually to allow for batch or pack sizes.

Why does a three-way match miss an over-shipment?

Because once the excess is booked on the goods receipt, the invoice and the receipt carry the same quantity. Unless the match also compares against the PO quantity, nothing disagrees.

Read next

Sources

Sources opened and checked Nov 2026.

The list sees it first

One essay a week, one wave at a time. Nothing you upload is ever kept.