The short answer
- A general rate increase (GRI) lifts a carrier's tariff rates across a trade; a peak season surcharge (PSS) is added in high-demand months.
- Whether either applies to contracted cargo depends on the contract: rates fixed for the term, surcharges included in an all-in rate, or allowed only after a stated notice period.
- The test is a date: when the shipment was booked or received, against when the surcharge took effect and when notice ran out.
- In US ocean shipping, tariff increases normally need 30 days' notice, and a charge applies only if it was in effect when the carrier received the cargo.
The July budget review had one slide nobody wanted: freight 18% over plan on the trans-Pacific lanes, explained in a single word, market. The contract with the forwarder fixed rates until the end of September, all-in, with peak surcharges allowed only on thirty days' written notice.
The notice existed. It had arrived on the 3rd of June in a shared mailbox that a departed colleague used to watch. The bookings came from the plant's planner, most of them in the second week of June. The containers sailed in July, and every invoice carried a new line: PSS, 600 per box.
The surcharge was real. For most of those boxes, it had not yet begun.
What are GRIs and peak season surcharges?
Ocean carriers publish tariffs: public price lists for their services. A service contract or a forwarder's rate agreement fixes prices for a named shipper, lane and period. A GRI raises the tariff; a PSS adds a line to it. Contracted cargo is touched only as far as the contract lets these flow through.
| Contract wording | Is a new GRI or PSS billable? | What decides |
|---|---|---|
| Fixed rates for the term | No, until the term ends | The validity dates |
| All-in rate including PSS | No separate line; it is already in the rate | The list of included charges |
| Allowed with notice | Yes, after the notice period has run | The notice date and the shipment's rating date |
| Subject to carrier tariff | Often yes, as the tariff changes | The tariff's effective date when cargo is received |
The rating date (booking, gate-in or sailing) is the detail most contracts leave vague, and the one most disputes turn on.
The notice clock and the booking date
A surcharge with notice is a clock. It starts when the notice is published or sent, and it ends on the effective date. What matters is where each shipment sits on it.
Peak months bring real cost pressures too, such as rolled cargo and blank sailings. The leak here is narrower: a charge reaching cargo the contract had already priced.
The signs already in your files
A surcharge line on its own proves nothing; many are allowed. The pattern needs records that disagree on dates:
- Your contracts and rate cards state the validity period and the GRI or PSS rule: excluded, included, or allowed after notice.
- Your freight invoices carry GRI or PSS lines on contracted lanes.
- Your bookings and tracking milestones show booking or gate-in dates before the surcharge took effect, or before notice ran out.
- Your general ledger shows cost per container stepping up in the month a surcharge was announced, on lanes whose rates were fixed.
What it costs, told honestly
Each pool against its own total, never added together. Invented numbers for one forwarder over a peak quarter:
| Pool | Total | Of which | Share |
|---|---|---|---|
| Freight | 640,000 billed on contracted lanes | 54,000 PSS on boxes booked inside the notice period | 8.4% |
| Cash timing | 590,000 paid to the forwarder | 42,600 of that surcharge already paid | 7.2% |
| Bookings | 112 bookings in the quarter | booked before the PSS could apply | 90 of 112 |
The budget variance called 'market' holds these same dollars. It is where the leak becomes visible, not a second loss.
How the world answers
Regulators on three continents have drawn the same line in different ink: a charge applies from the date it was properly in force, and not before.
United States Thirty days, and no shortcut without proof · 2024–2026
US rules require 30 days between publishing a tariff increase and applying it, and a charge applies only if it was in effect when the carrier received the cargo. When Red Sea attacks pushed carriers to add surcharges in early 2024, the Federal Maritime Commission granted some requests to shorten the notice, but its chair said approval did not endorse a charge's level or reach cargo already received, and warned about hidden rate increases.
In March 2026, as carriers added surcharges over the Strait of Hormuz crisis, the Commission rejected requests from CMA CGM, Hapag-Lloyd, Maersk and Zim to shorten notice, saying higher costs had to be tied to the dollar amount of the surcharge with supporting data.
Last effect: the Commission said in March 2026 it was reviewing the new Hormuz surcharges for compliance with the Shipping Act.
China Filed rates, applied rates · 2025–2026
China requires container lines and NVOCCs (forwarders that issue their own bills of lading) to file freight rates with the Ministry of Transport. After inspections at Guangzhou, Qingdao and Ningbo in August, September and November 2025, the ministry published penalties in May 2026 on 16 companies, nine container lines and seven NVOCCs, for filing lapses and differences between filed and applied rates. Amounts were not disclosed.
Last effect: the ministry held regulatory talks with the more serious cases and said it would step up filing inspections.
Nigeria A new tariff, applied too early · 2023–2025
A terminal operator applied a newly approved tariff, in force from 25 October 2023, to an importer's general cargo that had arrived earlier in 2023. The importer complained to the Shippers' Council. The Council found the cargo fell within the old tariff window and directed revised invoices at the old rate by the end of December 2025; it also waived charges for a period when the importer's letters went unanswered.
Last effect: the Council reported over ₦100 million in demurrage and terminal charges saved on cargo worth $341,256, with payment due by 30 December 2025.
Questions to ask before you act
- Does the contract fix rates for its term, include surcharges in an all-in rate, or allow them after notice? How many days?
- Which date rates a shipment: booking, gate-in, or sailing?
- When was each surcharge notice received, and by whom?
- Which of these invoices are still unpaid?
Frequently asked questions
What is a peak season surcharge?
An extra charge carriers add per container or per kilo in high-demand months, usually announced with a start date. Whether it applies to contracted cargo depends on the contract.
What is a GRI in shipping?
A general rate increase: a carrier raises its published tariff rates on a trade lane from a set date. Fixed-rate contracts usually shield cargo until the contract ends.
How much notice must ocean carriers give for rate increases?
In the United States, tariff increases normally need 30 days' notice, unless the Federal Maritime Commission grants special permission for a shorter period. Other countries set their own filing and notice rules.
Can I refuse to pay a peak season surcharge?
It depends on your contract's wording and dates. If the rate was fixed or the notice had not run when the cargo was booked or received, the charge can be disputed within the contract's window.
Read next
Sources
- FMC: Commission advisory regarding Red Sea surcharges, Jan 2024
- International Trade Today: FMC chairman on surcharge waivers, Feb 2024
- gCaptain: FMC warns shipping lines over Hormuz crisis surcharges, Mar 2026
- FreightWaves: FMC rejects carrier request for shorter notice, Mar 2026
- Maritime Executive: China fines MSC, CMA CGM and Hapag, May 2026
- IAPH World Ports: China fines 16 companies over freight-rate filings, May 2026
- Nigerian Shippers' Council: release of BUA Cement consignments
- Nigerian Shippers' Council: complaints newsletter, Oct-Dec 2025
Sources opened and checked Nov 2026.