The short answer
- A time bar is the deadline after which a cargo claim can no longer be brought, however clear the carrier's fault.
- Ocean (Hague-Visby Rules): written notice at delivery, or within 3 days if the damage was not apparent; suit within one year of delivery.
- Air (Montreal Convention): a written complaint within 14 days of receipt for damage, 21 days for delay; without it, no action lies against the carrier. Suit within two years.
- US road and rail (Carmack): carriers may not set less than nine months to file a claim, or less than two years to sue after a written refusal.
- The clocks run from delivery, not from the day someone opens the box.
The dock receiver signed for twenty-two pallets of tiles on a Thursday afternoon, in the rain, with trucks queuing behind. The receipt said nothing but a name and a time. Six weeks later, a picker in aisle nine pulled a pallet and heard it rattle. Four more pallets rattled the same way.
Quality emailed photographs to the forwarder, who promised to "look into it". Purchasing replaced the tiles from stock. Fourteen months after delivery, a new claims coordinator found the photographs and sent a formal claim. The carrier replied in two lines: time-barred.
The tiles were broken at sea. The claim was broken in the office.
What is the time limit for a cargo claim?
There are usually two clocks. The notice tells the carrier something is wrong while the evidence still exists. The time bar is the last day to start a lawsuit or arbitration. Missing the first weakens a claim; missing the second ends it.
| Mode and regime | Notice | Time to sue | Runs from |
|---|---|---|---|
| Ocean, Hague-Visby Rules | In writing at delivery; within 3 days if damage not apparent | One year (can be extended by agreement after the event) | Delivery, or when the goods should have been delivered |
| Air, Montreal Convention | In writing: 14 days for damage, 21 days for delay | Two years | Receipt (notice); arrival at destination (suit) |
| US road and rail, Carmack | Written claim: carrier may not set less than 9 months | Not less than 2 years | The carrier's written refusal of the claim (suit) |
| Forwarder or 3PL terms | Set by the contract | Set by the contract, often shorter | Read the terms on the booking |
Summary only. The transport document and route decide which regime applies.
Under Hague-Visby, a late notice does not kill the claim by itself: the clean receipt becomes evidence of good order, and the burden moves to the receiver. Under the Montreal Convention, without a written complaint in time no action lies against the carrier, unless it acted fraudulently. The air clock hurts fastest.
Where the deadline is really lost
Claims are rarely lost by choice. They are lost between rooms:
Insurance does not always catch the fall: where a missed notice destroyed the insurer's right to recover from the carrier, cover may be reduced, depending on the policy wording. And a claim that survives on time can still be capped by the carrier's liability limit.
The signs already in your files
One late claim can be bad luck. A habit shows when separate records line up:
- Your receiving log records damage or shortage on one date, or a receipt marked clean with damage logged days later.
- Your claims register shows claims filed after the deadline for the mode, or a status of "rejected: time-barred".
- Your transport documents (bill of lading, air waybill, road consignment note) name the mode and the carrier, and so the clock that applied.
- Your delivery receipts were signed without exceptions on shipments later found damaged.
What it costs, told honestly
Each pool against its own total, never summed. Invented numbers for one year of claims:
| Pool | Total | Of which | Share |
|---|---|---|---|
| Recovery | 148,000 claimed on all cargo claims filed | 78,300 claimed after the deadline for the mode, or rejected as time-barred | 53% |
| Goods and stock | 64,800 landed value of the damaged tiles | 64,800 recovered from neither carrier nor insurer | 100% |
| Damaged deliveries | 17 deliveries later found damaged | receipt signed with no exception noted | 11 of 17 |
The tile loss sits inside the late-claim value in the first line; it is shown again only against the goods it belongs to.
How the world answers
Two courts, two modes: one held a bank to the year, one counted the days and let a claim through.
United Kingdom (cargo: Indonesia to India) One year means one year · 2018–2024
About 85,510 tonnes of steam coal were shipped from Indonesia on the GIANT ACE and discharged at Jaigarh, India, in April 2018. FIMBank, holding the 13 bills of lading, alleged that the coal was released after discharge to parties not entitled to it, and started arbitration against the carrier, KCH Shipping, on 24 April 2020, about two years later.
The bank argued that the Hague-Visby Rules stop at discharge, so a six-year English limitation period should apply. It lost before the tribunal, the High Court and the Court of Appeal. On 13 November 2024 the UK Supreme Court unanimously dismissed the appeal: the one-year time bar covers misdelivery after discharge too. The point of the bar, it said, is finality.
Last effect: the judgment, [2024] UKSC 38, is final; under English law a cargo owner now has one year for misdelivery claims after discharge, as for loss and damage.
France Saved on the last day · 2012–2018
Research material flew from the United States to Sanofi's research centre in Montpellier. On 26 July 2012 the receiver noted that the temperature had gone out of range, and the cargo was useless. The written complaint was handed to the carrier's representative on 9 August 2012.
The carrier argued it was late. On 20 March 2018 the Court of Appeal of Montpellier held that the Convention alone governs the count, but the carrier's own conditions started the 14 days on the day after receipt, which favoured the shipper and is allowed. The deadline ran out at midnight on 9 August: the complaint was in time.
Last effect: the claim survived the time objection. The case record we read reports the ruling on time, not any amount paid.
Questions to ask before you act
- On what date was the damage first noticed, and was it written on the delivery receipt?
- Was written notice sent to the carrier named on the transport document, and is its date on file?
- Which regime applied: the convention for the mode, or the forwarder's own terms?
- Did anyone ask the carrier for a time extension in writing before the year ran out?
- Did the insurer reduce cover because the carrier claim was lost?
Frequently asked questions
How long do you have to file a cargo claim?
It depends on the mode and the contract. Under the Hague-Visby Rules, suit must be brought within one year of delivery; under the Montreal Convention, a written complaint is due within 14 days for damage and suit within two years; under Carmack in the US, carriers may not set less than nine months to file a claim.
Can the one-year Hague-Visby time bar be extended?
Yes, by agreement between the parties after the cause of action arises. The extension should be in writing and agreed before the year runs out.
Is an email to the forwarder enough notice?
It may not be. Notice should be written, dated and sent to the carrier or its agent; forwarder terms say who must receive it and by when.
Read next
Sources
- UK legislation: Carriage of Goods by Sea Act 1971, Schedule (Hague-Visby Rules)
- Justice Laws Canada: Carriage by Air Act, Montreal Convention text
- Cornell LII: 49 U.S. Code § 14706 (Carmack)
- Cornell LII: 49 U.S. Code § 11706 (Carmack, rail carriers)
- UK Supreme Court: FIMBank plc v KCH Shipping Co Ltd, case page
- UK Supreme Court: press summary, [2024] UKSC 38
- Pro-Aero (Université de Lorraine): Cour d'appel de Montpellier, 20 March 2018, no. 16/00330
Sources opened and checked Nov 2026.