The Kraljic matrix: four boxes that decide how hard to work each purchase

Not every purchase deserves the same effort. The Kraljic matrix sorts what a company buys by how much it matters to profit and how risky it is to get, then suggests a different approach for each group.

OpEx 3Ws5 min readUpdated 19 Nov 2026Facts checked Nov 2026

The short answer

  • The Kraljic matrix is a purchasing portfolio tool published by Peter Kraljic of McKinsey in the Harvard Business Review in 1983.
  • It places each purchase category on two axes: profit impact (how much it affects cost, quality or margin) and supply risk (how hard and uncertain it is to obtain).
  • That gives four quadrants: non-critical, leverage, bottleneck and strategic, each with its own buying approach.
  • It is meant for categories, reviewed periodically, not as a permanent label on individual suppliers.

What is the Kraljic matrix?

The Kraljic matrix is a two-by-two grid for deciding how to source each thing a company buys. Kraljic's 1983 article argued that purchasing should become supply management: instead of treating every item the same way, a company should match its effort to how much each item matters and how exposed its supply is.

The two axes are judged per category, such as packaging, castings, electronic components, freight or office supplies:

  • Profit impact: the category's effect on the bottom line, through spend, its share of product cost, its effect on quality, or its role in growth.
  • Supply risk: how hard the category is to secure, through the number of capable suppliers, scarcity, entry barriers, switching cost, technology change or logistics complexity.

The four quadrants

QuadrantProfit impactSupply riskTypical approach
Non-criticalLowLowMake buying efficient: catalogues, standard terms, fewer transactions, less buyer time
LeverageHighLowUse buying power: tenders, regular renegotiation, volume consolidation
BottleneckLowHighSecure supply: stock buffers, longer agreements, backup sources, redesign to widen the market
StrategicHighHighLong-term partnerships, joint planning, market monitoring, make-or-buy reviews, developing alternatives

Examples vary by company. Packaging may be non-critical for one firm and strategic for a beverage maker whose bottle is its brand.

LEVERAGEBOTTLENECKVSbig spend, many supplierspush on price and termssmall spend, few suppliersprotect supply firstPush on one. Protect the other.
Opposite instincts. Pressing a bottleneck supplier as hard as a leverage supplier can cost more in lost supply than it saves in price.

How to build a Kraljic matrix

From spend data to a sourcing planGroup the spendsplit purchases intocategories, not suppliersScore impactcost share, quality effect,margin, growthScore risksuppliers, scarcity,switching, lead timesPlace on the gridagree the scores withengineering and financePlan and reviewone approach per quadrant,rescored yearly
Scoring risk is the hard part. Spend is in the ledger, but supply risk needs judgement from people who know the market, the parts and the suppliers.

Scores are often set on a simple 1-to-5 scale per factor, with weights agreed in advance. The exact numbers matter less than the conversation they force: engineering often knows that a cheap part has only one qualified maker, which spend data alone never shows.

A worked example

Invented numbers. A lab-equipment maker scores four categories from 1 (low) to 5 (high).

CategoryImpactRiskQuadrantWhat changes
Office and cleaning supplies11Non-criticalMove to one catalogue and a purchasing card
Corrugated packaging42LeverageTender every two years across five suppliers
Custom sealing rings25BottleneckHold 12 weeks of stock and qualify a second maker
Precision optics54StrategicJoint forecast and a three-year agreement

The sealing rings cost little, yet a missing ring stops a 40,000 dollar instrument from shipping. Without the matrix, they would sit with office supplies as "low spend".

Common Kraljic matrix mistakes

Suppliers, not categoriesOne supplier can sell items in several quadrants. Labelling the supplier as a whole hides that mix, a misuse purchasing researchers have long pointed out.
Spend as impactUsing spend alone for the vertical axis pushes big, simple categories up and hides cheap parts that stop the line, as told in one supplier, one part.
Drawn once, never movedA tariff, a merger or a new regulation can move a category across the grid in a quarter. A matrix that is not rescored becomes a picture of last year's market.

Questions to ask before you act

  1. Are the boxes filled with categories, or with supplier names?
  2. Who scored supply risk, and did engineering and logistics have a say?
  3. Is profit impact measured by more than spend?
  4. When was the matrix last rescored, and what has changed in the market since?

Frequently asked questions

What are the four quadrants of the Kraljic matrix?

Non-critical (low impact, low risk), leverage (high impact, low risk), bottleneck (low impact, high risk) and strategic (high impact, high risk).

Who created the Kraljic matrix?

Peter Kraljic, then a director at McKinsey, in the 1983 Harvard Business Review article "Purchasing Must Become Supply Management".

What are the axes of the Kraljic matrix?

Profit impact of the purchase on one axis and supply risk, or supply market complexity, on the other.

What is a bottleneck item?

A purchase with low profit impact but high supply risk, such as a cheap part with only one qualified maker. The focus is on securing supply rather than on price.

Is the Kraljic matrix still used?

Yes, widely, as a starting point for category strategy. Common criticisms are that it is static and that it is often applied to suppliers instead of categories.